Project Updates

I am text block. Click edit button to change this text. Lorem ipsum dolor sit amet, consectetur adipiscing elit. Ut elit tellus, luctus nec ullamcorper mattis, pulvinar dapibus leo.

This is custom heading element

Project Description Scheduled
Start
Scheduled
Completion
Status Update
Fill Lake Tapps; Lake full all summer Bring lake to highest allowable level (543′) July 2014 July 2014 Completed
Barrier Dam Repair July 2014 July 2014 Completed
Flowline Outage

Click for additional details

Remove sediment; maintenance; About 75,000 cubic yards were removed. July 2014 September 2014 Completed