Project | Description | Scheduled Start |
Scheduled Completion |
Status Update |
---|---|---|---|---|
Fill Lake Tapps; Lake full all summer | Bring lake to highest allowable level (543′) | July 2014 | July 2014 | Completed |
Barrier Dam | Repair | July 2014 | July 2014 | Completed |
Flowline Outage | Remove sediment; maintenance; About 75,000 cubic yards were removed. | July 2014 | September 2014 | Completed |